London Bridge Network Rail Station
Client: Costain's
Completed: Ongoing

We are currently installing around 1000m2 of Delta cavity drain membrane to the brickwork arches which are due to be fitted out in to retail units.  We are also installing stainless steel stop trims and water collection gully's to accompany the system.  This project has been an interesting and challenging one where we have taken on the full design responsibility for the water management system, we are due to move on to the Western Arcade area in the station following completion of the retail units.