Concrete Repairs, Runnymede Leisure Centre
Client: Castle Point Borough Council
Completed: December 2017
Duration: 12 weeks

Prestec have just completed this extensive concrete repair project to the swimming pool at Runnymede Leisure Centre in Thundersley, Benfleet.

Our full scope of works included the removal of the asbestos ceiling panels in the swimming pool under-croft, steel reinforcement replacement where necessary, gunite sprayed concrete repairs and the installation of a DuoGuard Hybrid Anode steel reinforcement anti-corrosion system.

There were numerous areas around the concrete structure that also required water stopping techniques using resin injection, Prestec undertook these works using Drytech Dryflex-2 acrylic resin.